Grid
7 min read
Reading a substation’s spare capacity from public filings
Hosting capacity maps are patchy. Interconnection filings fill the gaps if you know where to look.

Written by
Veldt Research
Notes from the Veldt research team on grid, permitting, terrain and the business of getting land through diligence.
Where the data hides
Utility hosting capacity maps are useful but partial. Many are updated yearly and leave whole feeders blank. Interconnection queue filings, by contrast, are updated continuously and tell you exactly how much capacity has already been spoken for.
Building the picture
Veldt joins the two sources and resolves them to the nearest substation for every candidate parcel. The output is a distance, a voltage and an honest estimate of spare capacity, with a confidence band so you know when to call the utility.
Treat the number as a screen, not a study. It tells you which sites deserve a formal capacity request, and which ones never will.